Exam4Help-Get PMP PMI Free Demo Questions
Question No 4
What defines the portion of work included in a contract for items being purchased or
acquired?
A
. Procurement management plan
B
. Evaluation criteria
C
. Work Breakdown Structure (WBS)
D
. Contract Statement of Work (SOW)
Answer: D